1. Met Larvotto Interior Design Kane Saw at Larvotto Interior Design Office in Tradehub 21 and make the initial deposit of cash SGD 1,000.00 paid to Larvotto Interior Design thru PayNow on 27 Jul 2023.
2. 12 Aug 2023 - 1st meeting to discuss with Larvotto Interior Design Kane Saw on the laminate colour, wall paint colour and design of the wardrobes, TV wall and cabinets. Was informed that the 3D should be out in 2 weeks time.
3. On 4 Sep 2023, we ask Larvotto Interior Design Kane Saw about our 3D, was told need another week.
4. Larvotto Interior Design Kane Saw sent us the first 3D on 18 Sep 2023. But wall colour wrong, some of the design we discuss also wrong. From 12 Aug 2023 to 18 Sep 2023 (1 month and 6 days) colour wrong, design wrong and is done by a chief designer.
5. 22 Sep 2023 Larvotto Interior Design Kane Saw resent 3D drawing to us.
6. We got our key on 29 Sep 2023, Larvotto Interior Design Kane Saw came down site survey, we informed Larvotto Interior Design Kane Saw that we need to shift in on 02 Dec 2023, and he committed that he will clean up and hand over the fully renovated house to us on 27 Nov 2023.
7. 07 Oct 2023, site survey with Larvotto Interior Design Kane Saw and the carpenter, did some adjustment to the shoe cabinet and also master room wardrobe, need to redraw these 2 cabinets.
8. Make a Cheque payment of SGD 3,000.00 to Larvotto Interior Design Kane Saw at Larvotto Interior Design Office in Tradehub 21 on 12 Oct 2023.
9. 19 Oct 2023, chief designer hospitalised, our 3D still not done. Was told if there are minor rework on the 3D should be very fast don't need to re queue but how come from 7 Oct 2023 to 19 Oct 2023 almost 2 weeks our minor rework of the 3D cannot be done by the CHIEF DESIGNER!
10. We sent a complain WhatApps Message on 19 Oct 2023 highlighting all the issues relating to the 3D designs.
11. On 20 Oct 2023, Larvotto Interior Design Kane Saw informed that Larvotto Interior Design agreed to change another 3D Designer to redo our 3D Drawings, but can only give us the 3D Drawing on 24 Oct 2023.
12. On 24 Oct 2023 Morning, Larvotto Interior Design Kane Saw informed that the 3D Desginer’s computer is corrupted, therefore unable to send us our 3D Drawings.
13. On 24 Oct 2023 (2304hrs), Larvotto Interior Design Kane Saw forwarded our 3D Drawings to us.
14. On 25 Oct 2023, we informed Larvotto Interior Design Kane Saw to start the carpentry fabrications for most of the wardrobes, platforms, and kitchen Cabinets.
15. Make a Cheque payment of SGD 12,000.00 to Larvotto Interior Design Hong Yi at Larvotto Interior Design Office in Tradehub 21 on 26 Oct 2023, as Larvotto Interior Design Kane Saw was not in Singapore.
16. After reviewing the shoe cabinets and TV console, informed Larvotto Interior Design Kane Saw to proceed with the carpentry fabrications on 26 Oct 2023.
17. Larvotto Interior Design Kane Saw informed that the fabrications will take 2 to 3 weeks to complete and based on the schedule the installation of all the carpentries will be commencing on 13 Nov 2023 that week.
18. Make a Cheque payment of SGD 10,500.00 to Larvotto Interior Design Hong Yi at Larvotto Interior Design Office in Tradehub 21 on 05 Nov 2023, Larvotto Interior Design Kane Saw was not in Singapore.
19. 05 Nov 2023, lay protection for the floor.
20. 07 Nov 2023, tiling, plumbing and false ceiling start.
21. 12 Nov 2023, painting for the house.
22. Larvotto Interior Design Kane Saw sent revised schedule the carpentry installation can only start on 21 Nov 2023, which is about 1 week late as compare to the initial schedule.
23. Shower Screen contractors came to install the shower screen on 18 Nov 2023, but only the common toilet is installed, the master bedroom was not installed. Larvotto Interior Design Kane Saw informed that the measurement was wrong.
24. 21 Nov 2023, carpentry installation start with only one installer (not the worker who fabricate the carpentries) doing the installation.
25. We found out the platform for bedroom 3 was wrong, the fabricated platform was less than the agreed 57sqft. This error was found out on 22 Nov 2023. Immediately informed Larvotto Interior Design Kane Saw and Larvotto Interior Design Hong Yi.
26. We also found out that master bedroom wardrobe should be sling door but the delivered item is a casement door wardrobe.
27. The top hang cabinet in bedroom 3, contractually is 5ft, but the delivered cabinet is only 3ft.
28. There was NO onsite supervision from Larvotto Interior Design Kane Saw since 12 Nov 2023. We have been doing all the supervision since the project started.
29. We lodged a complained to Larvotto Interior Design Francis Tham on 23 Nov 2023 as there were no carpentry works done on 22 Nov 2023 and 23 Nov 2023.
30. Larvotto Interior Design Francis Tham informed us on 23 Nov 2023 that our carpentry installation will be completed in 3 days (i.e. 26 Nov 2023).
31. On 24 Nov 2023, 2 installers (not the worker who fabricate the carpentries) came to install and on 25 Nov 2023 only 1 installer (not the worker who fabricate the carpentries), on the 25 Nov 2023, we found out that the shoe cabinet is too long and it was wrong dimension as agreed in the contract.
32. We requested for a site meeting on 25 Nov 2023@1400 with Larvotto Interior Design Francis Tham, Larvotto Interior Design Hong Yi and the carpentry vendor.
33. As the platform sized is wrong, the study table dimension is wrong too. Carpentry Vendor suggested to do extension to the table which we strongly refused and demanded to fabricate a new table.
34. After the site meeting, Larvotto Interior Design Francis Tham informed that all carpentry works will be completed on 28 Nov 2023 which is another 2 more days of delay.
35. The handover of the project shifted from 27 Nov 2023 to 30 Nov 2023.
36. Since 21 Nov 2023, the start of the carpentry installation, we have request and even pleaded with Larvotto Interior Design Francis Tham and Hong Yi to get more installers and workers from the Carpentry Vendor to help install our carpentry but to no avail.
37. We must accept the Master Bedroom casement door wardrobe instead of sling door as the rework will further delay the completion of the project.
38. The over length shoe cabinet was not redone, the installer (not the worker who fabricate the carpentries) onsite cut off the excess length and the contracted 5 ft became 4.11ft.
39. The finishing and quality of the carpentry works are poor as these are rushing works since the beginning of the project.
40. Installation of 3 x 6ft wardrobes, 2 x 11ft top and bottom kitchen cabinets, 1 x 8.5ft bottom kitchen cabinet, 1 x 4ft service yard bottom cabinet, 57sqft platform, 1 x 5ft TV console and cabinet, 1 x 5ft shoe cabinets took 8 days to complete (21 Nov 2023 – 28 Nov 2023)
41. All the mistakes were spotted by us as we have been doing site supervision since the day when the installation starts, imagine if we were not present during the installation, what will be catoptric outcome it will be.
42. Larvotto Interior Design is totally unprofessional starting from 3D Design (wrong colour even after we have clearly indicated what colour we wanted), take more than 45 days to provide a 3D Drawing, communicated that our shifting date is on 02 Dec 2023 since the initial meetings but still did not put in effort to ensure all planned schedule are adhere to and completed on time. Worst part of all, the dimensions of those critical items are wrong even after we have site survey and measurement.
43. Larvotto Interior Design is not customer centric; we highlight our concern but was not taken seriously. We saw the issues when the installer (not the worker who fabricate the carpentries) starts to do installation, only 1 or 2 installers in the initial phase, they are not the one who fabricate the cabinets, they need time to find and even call the carpentry boss to verify which is which. We highlighted that the right person and the number of carpentry workers should be doing our installation but none of our suggestion or plead was taken seriously.
DesignMainly designs come from us, the false ceiling and cove light are designed by myself. The main door shoe cabinet also our ideas.
WorkmanshipInstallation of 3 x 6ft wardrobes, 2 x 11ft top and bottom kitchen cabinets, 1 x 8.5ft bottom kitchen cabinet, 1 x 4ft service yard bottom cabinet, 57sqft platform, 1 x 5ft TV console and cabinet, 1 x 5ft shoe cabinets took 8 days to complete (21 Nov 2023 – 28 Nov 2023)
The platform dimensions was wrong initially and it was discovered by me on-site.
The shoe cabinet is too long also discovered by us onsite.
Customer ServiceLarvotto Interior Design is totally unprofessional starting from 3D Design (wrong colour even after we have clearly indicated what colour we wanted), take more than 45 days to provide a 3D Drawing, communicated that our shifting date is on 02 Dec 2023 since the initial meetings but still did not put in effort to ensure all planned schedule are adhere to and completed on time. Worst part of all, the dimensions of those critical items are wrong even after we have site survey and measurement.
Larvotto Interior Design is not customer centric; we highlight our concern but was not taken seriously. We saw the issues when the installer (not the worker who fabricate the carpentries) starts to do installation, only 1 or 2 installers in the initial phase, they are not the one who fabricate the cabinets, they need time to find and even call the carpentry boss to verify which is which. We highlighted that the right person and the number of carpentry workers should be doing our installation but none of our suggestion or plead was taken seriously.
Value for MoneySince 21 Nov 2023, the start of the carpentry installation, we have request and even pleaded with Larvotto Interior Design Francis Tham and Hong Yi to get more installers and workers from the Carpentry Vendor to help install our carpentry but to no avail.
We must accept the Master Bedroom casement door wardrobe instead of sling door as the rework will further delay the completion of the project.
The over length shoe cabinet was not redone, the installer (not the worker who fabricate the carpentries) onsite cut off the excess length and the contracted 5 ft became 4.11ft.
The finishing and quality of the carpentry works are poor as these are rushing works since the beginning of the project.